Roof Slab Concreting Checklist: Before, During and After the Pour
A slab is poured in one day and lives for decades. This checklist covers every step from formwork inspection to de-shuttering.

Before a roof slab pour, check formwork level, props and joints; verify steel bar sizes, spacing, laps and cover blocks against the drawing; fix conduits and sleeves; and stock all cement, sand, aggregate, water and equipment. During the pour, place concrete continuously from one end, compact with vibrators, avoid extra water and take cube samples. After the pour, protect the surface, cure for at least 7–14 days and remove props only when the engineer allows.
Before the pour
Formwork
- Shuttering level and at correct height; camber if specified.
- Props plumb, at specified spacing, on firm base plates or sole plates.
- Joints tight — no gaps for slurry to leak.
- Shuttering oil applied; surface cleaned of debris, wire and sawdust.
Reinforcement
- Bar sizes, spacing and number match the structural drawing.
- Laps and anchorage lengths as specified; laps staggered.
- Cover blocks of the correct thickness under bottom bars and at edges.
- Chairs holding top steel at the right height.
- Steel clean — no loose rust, mud or oil.
- Engineer's inspection and approval recorded.
Services
- Electrical conduits and junction boxes fixed and taped.
- Plumbing sleeves for pipes placed.
- Fan hooks and any embedded fixtures in position.
Materials and equipment
- Cement, sand, aggregate and water for the entire pour plus 5%. Calculate with the slab material calculation.
- Mixer and a standby, two or more needle vibrators, a lift or ramp, gauge boxes, buckets.
- Cube moulds cleaned and oiled.
- Lighting if the pour may run late; polythene in case of rain.
- Enough labour for continuous work.
During the pour
- Start from one end (usually the far end) and work towards the access point.
- Pour continuously — avoid interruptions that create cold joints. If a stop is unavoidable, form a construction joint where the engineer specifies.
- Measure every batch with gauge boxes and measured water. See water-cement ratio.
- Do not drop concrete from height — it segregates.
- Vibrate thoroughly, especially around beams, column junctions and congested steel. Do not use the vibrator to move concrete sideways.
- Keep checking cover — workers walking on steel can push bars down.
- Level and finish with screed boards; float at the right time.
- Take cube samples as per specification for 7- and 28-day tests.
After the pour
- Protect from sun, wind and rain as soon as finishing is done.
- Start curing once the surface can take water; pond with mortar bunds. See curing methods.
- Cure for at least 7 days (OPC) or 10 days (blended); 14 days is common practice.
- No heavy loads — do not stack bricks or cement on a new slab.
- De-shuttering: IS 456 gives minimum stripping times with OPC in normal weather — about 3 days for slab soffits with props left under, and props under slabs spanning up to 4.5 m after 7 days and over 4.5 m after 14 days. Blended cements and cold weather may need longer. Follow your engineer.
Key takeaways
- Inspect formwork, steel, cover and services before pouring.
- Stock all materials and backup equipment for a continuous pour.
- Compact well, avoid extra water, take cube samples.
- Cure properly and remove props only when approved.
Frequently asked questions
How many days after casting can slab shuttering be removed?
IS 456 gives minimum times for OPC in normal weather: soffit formwork after about 3 days with props re-propped, props under slabs up to 4.5 m span after 7 days and over 4.5 m after 14 days. Blended cements and cold weather may need longer; follow your engineer.
What is the cover for a roof slab?
Nominal cover depends on exposure; IS 456 specifies 20 mm for mild exposure and more for harsher conditions. Use cover blocks of the size in your drawing.
Should a slab be poured in one go?
Yes, ideally in one continuous operation. If a stop is unavoidable, form a construction joint at a location specified by the engineer.
Need materials for this work?
See indicative delivered prices for your pincode, or get an itemised project quotation with freight, unloading and GST shown line by line.
This guide is general information for planning and buying. Quantities, grades and methods for your structure must follow your approved drawings, your engineer’s specification and the applicable Indian Standards.